Interim storage building on river's edge and nuclear power plant further downstream

Safety Case Advice & Support

Safety Case Construction

A safety case is the totality of documented information and arguments which substantiates the safety of the nuclear power plant, activity, operation or modification in question. It provides a written demonstration that relevant standards have been met and that risks have been reduced As Low As Reasonably Practicable (ALARP).

The safety case generally contains three key stages in order to provide a comprehensive justification. These three stages are:

  • A Hazard Identification
  • Consequence Analysis
  • ALARP Justification

These stages encapsulate all the possible risks for a given system and through the information gathered and the data analysed during these processes constitute a comprehensive nuclear safety assessment. A System in this context is any facility, operation, activity or logic system which is being subjected to the risk assessment.

AFRY has developed considerable experience in producing Safety Cases for a wide variety of applications across the UK nuclear industry in both active nuclear facilities and facilities undergoing decommissioning for both civil and defence sector Clients. These include work on new build projects such as Hinckley C, performing safety lead for nuclear fuel storage and movement operations as well as independent nuclear safety assessment across a range of UK nuclear sites.

Supporting our customers in fulfilling nuclear safety requirements

The end-users of Safety Cases have a set of requirements that need to be met in order for the Safety Case to properly substantiate the site, building or operation. Meeting these requirements underpins the entire nuclear safety case process and so establishing these conditions is equally important.

It is necessary to establish and demonstrate in a written form that the plant, process, activity, modification etc. being proposed is safe. i.e.:

  • Soundly assessed and meets required nuclear safety principles
  • Conforms to good nuclear engineering practice, appropriate criteria, standards and codes of practice
  • Adequately safe during normal operation and fault conditions
  • Is and will remain fit for purpose
  • Risks to public and workers are ALARP.
Two engineers conversing in a turbine and generator hall of a nuclear power plant

Three key stages in building a Safety Case

Hazard Identification Arrow pointing right

One key part of any nuclear safety case would be the hazard identification process. This captures all of the possible hazards for a given system. The hazards are assessed determining severity, consequences and frequency. This information is fed back into the risk assessment providing quantitative data for the safety case.

Key to this hazard identification process is performing a Hazard and Operability Study (HAZOP). HAZOP is a ‘bottom up’ systematic technique used for the identification of hazards in any given system. The bottom up approach means that success rides on prediction by Experts based on previous experiences. HAZOP studies excel at analysing hazards in facilities, processes and equipment as well as identifying those that are hard to quantify, these could include Human Error hazards or ones that are difficult to detect and measure.

Methodology

HAZOP Studies consist of four phases: Definition, Preparation, Examination and Documentation.

Definition: is the initial stage of assessment and defines the scope and objectives and responsibilities of the study as well as assembling the team of assessors.

Preparation: this is the planning stage, where the time scale and schedule are determined. In this stage data on the system is also collected to inform the assessment.

Examination: is the largest stage of the assessment. The system is broken down into parts, the design intent for the part is determined and the guide words are applied. Guide words are a systematic set of words used to focus the study and stimulate consistent critical thought across the entire system. Once the consequences and causes of the hazards are identified it is determined whether a significant issue has been discovered. Then any protection or detection mechanisms and mitigating measure can be decided on by the team.

Documentation: this stage is the final part of the process. In here the examination is recorded and signed off on and any follow up procedures are determined and implemented.

Consequence analysis Arrow pointing right

A consequence assessment is a quantitative numerical estimation of the effects of a hazard on people (and the environment). This is an important step in the hazards assessment process as it provide a deeper understanding of the hazards identified in the HAZOP process. Two different methods of assessment are used during a consequence analysis, Deterministic and Probabilistic Safety Assessment (DSA & PSA).

Deterministic Safety Assessment aims to determine the effectiveness of “lines of defence”

Design Basis is the range of conditions and events taken explicitly into account in the design of a plant, so that the plant can withstand them without exceeding authorised limits, by the planned operation or safety systems. The objective is to demonstrate that there is in place an appropriate quantity of safety systems, which are of an appropriate quality (i.e. ability to prevent or mitigate the consequences). Deterministic Safety Assessment establishes and confirms the Design Basis for items important to safety, ensuring that the plant design meets safety and radiological criteria (integrity of barriers).

The required quantity of safety systems from Design Basis Accident Analysis is determined from two factors:

  1. The unmitigated consequences to the critical group (e.g. public / workers in cell / workers in corridor) from the fault.
  2. The initiating event frequency for the fault.

The calculation of both the unmitigated consequences and the initiating event frequency should incorporate demonstrable conservatism.

Probabilistic Safety Assessment analyses the risks associated with a system.

These risks are then expressed in terms of damage to the facility or the surrounding environment.

PSA uses realistic approach to risk as basis for the calculations, producing results that, in principle, give better understanding of the risk profile for the system over a wider range of operating modes than DSA. PSA also considers the system as a whole including any inter-system interactions providing additional information for the safety assessment.

In PSA there are two quantifiers in the analysis that allow for the determining of risk, these are the frequency and magnitude of a given consequence. Determining the magnitude for a given consequence included identifying the potential impact in terms of the dosage uptake for workers on site and for member of the public in the surrounding area. Consideration should be given to the use of realistic data when calculating consequences rather than conservative worst case scenarios.

Determining the frequency of a given consequence can be done through Event Tree (ET) and Fault Tree (FT) analysis.

Both techniques are a top down logical approach.

  • FTs run primary events, such as a valve failure, through Boolean logic to a undesired top event such a Loss of Coolant accident. The likelihood for each of these primary events failing is input to the model and thus frequency for a given consequence can be determined.
  • ETs are another logic driven process which starts with an initiating event. The event tree branches out to all the possible consequence that a given initiating event could cause. Providing a picture of what could happen should such a failure occur.

These two techniques can been used in conjunction, starting from the initiator event and following through the system events to eventual consequences, with each system event having a corresponding fault tree node with each node have split outcomes depending on the success or failure of the system event. So when combined the probabilities of all the consequences arising from that initiating event are visible.

ALARP Justification Arrow pointing right

The final part of the safety case is the ALARP or As Low As Reasonably Practicable Justification.

ALARP is a concept that allows duty holders to weight the risk against the time, funds and effort required to control a given hazard. ALARP is a flexible process that requires judgments to be made by safety assessors and duty holders on whether a risk can be classified as ALARP. Defining ALARP for complex systems, such as those found on nuclear sites, requires building on previous experiences and using formal analysis techniques in order to reach a decision.

To Satisfy a Safety Case it is necessary to show that the risks present in the system are shown to be ALARP. A Risk could be proven ALARP by ‘Best Practice’ or on ‘First Principles’. Best practices are determined beforehand by looking at previous examples and seeing if expected measures are in place, then a consensus of stakeholders can agree if the best practice has been achieved. In complex systems the ‘effort’ involved in mitigating a risk can be hard to quantify, so techniques such as a cost benefit analysis (CBA) can be used to numerically justify the ALARP.

ERIC PD is another analytical technique used in minimising risks and demonstrating that a given risk could be categorised as ALARP.

ERIC PD is an Acronym and each stage is defined below:

E – Eliminate – Redesign the system to remove the presence of the hazard.
R – Replace – Change the system by replacing the hazardous material/process/structure to reduce the hazard.
I – Isolate – Isolate the receptor group from the hazard by removing them from the vicinity or providing containment.
C– Controls – Use engineered measures to manage or reduce the hazard.
P – Protect – if the measures described fail to properly control a risk to ALARP then Personal Protective Equipment is issued to reduce the risk to anybody working with the system.
D – Discipline – Use of operational / administrative control measures to prevent or mitigate the hazard.

This systematic approach allows for a consistent approach to risk reduction even for complex systems which best practice justification isn’t possible.

Ringhals nuclear power plant with water reflection
Ringhals nuclear power station

Through this and other techniques AFRY's nuclear consultants have a deep understanding of what it required when producing a Safety Case, our team of consultants and experts have been involved in completing this type of documentation and analysis across the civil and defence nuclear sectors.

Hinkley Point C EPR NPP Site Specific Pre-Construction Safety Report
AFRY has provided support to EdF NNB Genco in the development of a Site Specific Pre-Construction Safety Report for Hinkley Point C.

Uranium Processing Facility Modification Safety Report, Safety Lead / Author / HAZOP Chair
Safety lead for a project to replace key components within the space extract system for a building within the Uranium Processing Facility complex.

Fuel Storage Pond Live Safety Case and Asset Care Projects
Safety Lead (Work Manager) role responsible for the management of S&RM deliverables for the fuel storage pond Live Safety Case (LSC) and associated asset care projects.

If you are interested is utilising our knowledge, please do not hesitate to contact us.

Dave Taylor - Head of Nuclear Safety and Design Section, UK
Dave Taylor
Head of Nuclear Safety and Design Section, UK

Interested in our offering? Contact us!

Contact Dave Taylor

For sales enquiries, please complete this form. For all other enquiries, please visit our office and contacts page here.

You may also be interested in: