International Paper STORK-PM4 rebuild
Project Goals
-
Implementation of very high quality stiff and bulky Alaska board with quality in the top 5% in the world
-
Capacity increase
DANE PROJEKTU:
FEL2: September 2011÷March 2012
FEL3: May 2012÷November 2012
Investment decision: March 2013
Start-up: April 2014
AFRY Services
(ówczesna nazwa Poyry Poland Sp. z o.o.)
-
FEL 2 level pre-engineering
- FEL 3 level pre-engineering
- Detail engineering
- Project in cooperation with Pöyry Finland
AFRY Poland sp. z o.o.
(ówczesna nazwa Poyry Poland Sp. z o.o.)
- Engineering management
- Process engineering
- Layout and mechanical engineering
- Piping engineering
- HVAC
- Electrical engineering
- Instrumentation and automation engineering
- Civil Engineering
AFRY Finland
- Project management
- Time-scheduling
- Cost estimation
Production
- High quality Arctica and Alaska board
Scope of Rebuild
Slushing plant
- New deflaking line
PM4
- Stock preparation
- Short circulation
- Broke system
- White water system
- Press section
- Dryer sections (pre- and postdryers)
- New ValZone calender
- Reel
- Coating section
- Winder
- Steam & Condensate system
- Machine hall ventilation
- Special rooms ventilation
- Heat recovery
- DCS & QCS
- PM drive (mechanical & electrical)
- Power distribution
Finishing Plant
- Two new folio sheeters
- Rolls supply system
- Trim & dust handling system